The overpass in Venizelosova in Novi Sad has been completed as part of the high-speed railway project

The construction of a new overpass in Venizelosova Street in Novi Sad has been completed, as part of the construction of a high-speed railway, and road traffic in one of the busiest city streets has been re-established. By the end of February, it is planned to put Temerinska Street into traffic, where the works on the reconstruction of the high-speed railway overpass are being completed, the company announced. Serbian railway infrastructure.

Illustration (Photo: Pixabay.com)

The work on Venizelosova lasted six months, the existing overpass was demolished, and a new one 30 meters long was built in its place. Instead of one track, there will be two tracks on the new overpass of the future high-speed railway. Concrete thresholds have been set, and the works on the approach to the bridge have yet to be completed, which does not endanger the safety and development of road traffic.

By the end of February, it is planned, according to the promise of the contractor RŽD international, Temerinska Street should also be opened to traffic, where the works on the reconstruction of the high-speed railway overpass are being completed. The overpass is 35 meters long.

In the future, the railway traffic on this overpass will run on three tracks, two of which will be intended for trains on high-speed lines, while one track will be used as an industrial track for the needs of the port in Novi Sad. Before the reconstruction of the railway, the traffic took place on two tracks, which caused the existing overpass to be expanded for the needs of another track during the works. With the new arrangement of the overpass on three tracks, the traffic will take place on a solid concrete base on which concrete thresholds will be installed.

Preparatory works in Temerinska Street began at the end of April 2020, during the state of emergency due to the corona virus pandemic, and have not been interrupted, while road traffic has been interrupted since this summer. In recent months, the works on the overpass have intensified, so that instead of the end of March, as expected, the traffic in this also very busy street will be released a month earlier.


Source: Gradjevinarstvo.rs – VESTI by www.gradjevinarstvo.rs.

*The article has been translated based on the content of Gradjevinarstvo.rs – VESTI by www.gradjevinarstvo.rs. If there is any problem regarding the content, copyright, please leave a report below the article. We will try to process as quickly as possible to protect the rights of the author. Thank you very much!

*We just want readers to access information more quickly and easily with other multilingual content, instead of information only available in a certain language.

*We always respect the copyright of the content of the author and always include the original link of the source article.If the author disagrees, just leave the report below the article, the article will be edited or deleted at the request of the author. Thanks very much! Best regards!