“Terex” sued RiTE “Ugljevik” for another 7.7 million KM

15.02.2021. / 16:31

BANJA LUKA – The company “Terex-engineering”, which in the past decade and a half has collected millions from the Mine and Thermal Power Plant “Ugljevik” for never done work, is trying to collect another 7.75 million KM from RiTE.

PHOTOS: Panradio

“Terex inženjering” is one of the companies to which RiTE “Ugljevik” had to pay a million amount for never performed works based on court rulings.

In a series of disputes over the past 15 years, RiTE paid Terex millions on several occasions, and then Terex returned them to the company after the verdicts in favor of RiTE.

The information prepared for tomorrow’s General Meeting of Shareholders by the management of RiTE “Ugljevik” states that “Terex” currently has at its disposal 2.79 million KM without a legal basis, and an additional 2.95 million KM for which it has a legal basis.

The company is faced with the fact that “Terex – Engineering” collected an additional 2.79 million KM, which is still available despite the fact that the decisions, on the basis of which it was collected, were revoked, and we are forced to we prove the existence of unjustified acquisition on the side of “Terex – engineering” Bijeljina and demand the return of that money “, is stated in the information.

Also, it is pointed out that “Terex” initiated a new dispute “heavy” 7.75 million KM, which is based on the request for the return of money that “Terex” returned to the mine and thermal power plant in the counter-enforcement procedure.

They explained that “Terex-inženjering” initiated a lawsuit against RiTE “heavy” 4.47 million KM with legal default interest with a lawsuit for unjust enrichment, and the court accepted the request for payment of the main debt while the part for interest was rejected.

Both companies appealed against this verdict, which the Higher Commercial Court in Banja Luka accepted in the middle of last year and returned to the first instance court for a new decision.

“During the retrial, Terex settled the claim, and instead of the original amount, it is now claiming 7.75 million with legal default interest.”, is stated in the information.

The verdict in this dispute was supposed to be passed on January 29, but that has not happened yet.

The dispute between “Terex Engineering” and RiTE “Ugljevik” has been going on since 2005. The lawsuit was filed after RiTE in 2003 in the public procurement procedure for the performance of auxiliary works on the open pit “Bogutovo Selo”, chose this and the companies “Šico company” and “Continental” as the most favorable, but the contracts with them were not concluded because The RS government instructed RiTE “Ugljevik” to produce coal and overburden by the end of that year with its own machinery.

Millions of disputes on the same basis with RiTE have been led by “Shico company” and “Continental” for years.

CAPITAL: Marina Čigoja Ljubojević


Source: Capital.ba – Informacija je capital by www.capital.ba.

*The article has been translated based on the content of Capital.ba – Informacija je capital by www.capital.ba. If there is any problem regarding the content, copyright, please leave a report below the article. We will try to process as quickly as possible to protect the rights of the author. Thank you very much!