How far has it come with the construction of the underground public garage “Banovina” in Novi Sad?

Rough works on the underground public garage near the Assembly of AP Vojvodina were completed at the end of 2022. This is the end of all earthworks and excavation works, as well as rough construction works related to the structural part of the building. At this moment, installation works are being carried out inside the buildingwhich will be followed by fine craftsmanship, finishing works.

The garage is expected to open by the end of the year

The opening of the garage is expected by the end of the year (Photo: Inobačka)

The company “Inobačka” doo as a general contractor engaged by “Javna Garaža” doo already during the summer will create the preconditions for the City of Novi Sad to begin work on the planned ground floor arrangement, all so that the citizens of Novi Sad could use the public garage until the end of this calendar year near the Banovina building.

The company “Javne Garaže” doo, which finances the entire implementation and equipping of public garages, covers all references necessary for the realization of this project, one of 4 underground public garages that are included in the same concession deal concluded with the City of Novi Sad as an investor. The financier of these projects is the company “Javne garaže” doo, which was founded by the company from Austria “Best in Parking” and the construction company “Inobačka” doo

“Best in Parking” is the majority owner of this company and is a renowned global company that operates numerous public garages in Austria, Germany, Switzerland, Italy, the Czech Republic, Slovenia, Bosnia and Croatia.

The entire project team engaged in this project gathers over 50 experts in various specialties. In addition to the company “Inobačka” doo, as the main contractor, a number of specialized companies in the field of construction, architecture, geomechanics, geotechnics, hydromechanics, geodesy, traffic, mechanical engineering, hydrotechnics, fire protection systems and electrical engineering participate in the construction process.

Plots and garages remain the property of the City of Novi Sad, and the company “Javne Garaže” pays the concession fee to the City. The project is financed by the company “Javne garaže”, therefore the City of Novi Sad does not allocate funds from the city budget to finance the construction of public garages.


Source: Gradjevinarstvo.rs – VESTI by www.gradjevinarstvo.rs.

*The article has been translated based on the content of Gradjevinarstvo.rs – VESTI by www.gradjevinarstvo.rs. If there is any problem regarding the content, copyright, please leave a report below the article. We will try to process as quickly as possible to protect the rights of the author. Thank you very much!

*We just want readers to access information more quickly and easily with other multilingual content, instead of information only available in a certain language.

*We always respect the copyright of the content of the author and always include the original link of the source article.If the author disagrees, just leave the report below the article, the article will be edited or deleted at the request of the author. Thanks very much! Best regards!