BIOMASS HEATING EQUIPMENT ARRIVED IN PRIBOJ

These days, the mechanical equipment for the new biomass heating plant that is being built in Priboj has started to arrive, it was announced on the municipal website.

– Four out of a total of 25 equipment trucks arrived from Austria, and in the first round are parts of the biomass boiler – says Saša Vasilić, Deputy Mayor of Priboj and adds that the rest of the equipment will arrive, successively, by the end of March.

According to him, there is a possibility that the heating plant will be put into trial operation before the deadline.

Along with the construction of the heating plant, project activities are underway on the reconstruction of substations and heating pipelines, which will otherwise be done after the end of the current heating season.

Let us remind you, the value of the investment with the reconstruction of the heating pipeline and the replacement of substations is EUR 7 million.

The plan is for all works to be completed by October 1, and the commissioning of the new city heating plant in Priboj on biomass is expected from the next heating season.

E2 portal (eKapija)


Source: E2 Portal by www.e2.rs.

*The article has been translated based on the content of E2 Portal by www.e2.rs. If there is any problem regarding the content, copyright, please leave a report below the article. We will try to process as quickly as possible to protect the rights of the author. Thank you very much!

*We just want readers to access information more quickly and easily with other multilingual content, instead of information only available in a certain language.

*We always respect the copyright of the content of the author and always include the original link of the source article.If the author disagrees, just leave the report below the article, the article will be edited or deleted at the request of the author. Thanks very much! Best regards!